Hey Brien,
Unfortunately, I did
not get the sand under the slab for a couple of reasons. The site excavated to depth was very wet. And something easily in the
Top 10 Things You Don't Want to Hear from Your Very Experienced Excavation Contractor When at Footer Depth is, "I haven't seen a spring like this in years." Right along with the DEP guy saying, "there are people who would kill for this flow-rate." Once we saw all this water flow, the only thing the inspector and builders were concerned with was footer size. The 'undisturbed earth' is entirely clay, the geological engineer analyzed a soil sample and determined the footer size needed for such a heavy structure was 42" W x 12" H for the perimeter and 42" x 12" under all of the other ICF interior walls too - as you probably saw. Water diverted, massive footers, inspectors satisfied, codes met, no sand.
In the opinion of people much smarter than I am, (basically everyone) including a geological engineer, building consultant/code expert doing the plans, the local inspector, and the 1st concrete contractor, the priority was adding drainage to give any water that might come up under the slab an unrestricted path to daylight. One or more suggested sand might be a bit of a risk eroding over time, since nobody can say for sure how water would behave under the slab. I asked about putting a vapor barrier or any other kind of barrier above AND below the sand. Nobody seemed 100% confident in that either in the long haul. So not knowing jack about it, I deferred to the guys with the building experience. So was I railroaded, or were they just unfamiliar / uncomfortable with the concept? Even though about a year had passed from the initial digging to the final drainage and footer dig, I spent most of the year waiting on the original concrete guy to fit me into his schedule. Then after I found the new guy through a friend who's a GC, it was only a couple weeks from the time I brought him onboard until there were 5 guys here finishing concrete. It went from zero to full bore pretty quickly and the sand was the last thing on my mind, so I'll take full credit for dropping the ball on that, and not pushing harder for finding a way to incorporate it. I was pre-occupied with trying to get some conduit in before the floor was poured and trying to anticipate any places conduit might be useful sleeved through the walls. In the end, I'd say it's no better or worse than any other typical basement floor in terms of sound / vibration. I did have a chance to visit Max's place several years ago, and the floor is really exceptional, but given the amount of gear in there, I don't know how freely the floor would vibrate even if it was a big drum head.
The final basement floor & wall assembly ended up almost like what's shown in this drawing from Post [
="http://recording.org/threads/building-to-begin-spring-09-icf-shell.36560/page-2#post-274958"]#23[/
], with the biggest differences being; 1) we ended up using a different brand of ICF form 2) unlike the drawing, they left the foam in place around the outer edge of the slab 3) they used 12" tall Form-a-Drain to form all of the footers to provide even better drainage both inside and outside the footer itself. And 4) they went way above and beyond on the rebar department, in the 10" core basement walls there is vertical rebar every 8" and horizontal rebar every 8" instead of every 12" and 16" as illustrated. The walls from there on up are 6" core and the vertical rebar is still every 8", but the horizontal rebar is every 18". Some of the pictures show rebar slightly further apart sticking up above the forms, but they're just dowels in the wet cement to pin one pour to the next (there were 6).
And I guess another part of the drawing below that's obviously complete BS is the notion that an excavator could carve out a notch at the bottom for the drainage and gravel outside the footer without removing any of the dirt above. So for better or worse, that's all back-filled with 2B gravel probably 3ft wide or more from the footer on up. So many tri-axle loads of gravel…...
In other 'thermal' related news, there are also 3 zones of PEX in the basement slab for radiant in-floor heat, which may not really be relevant to your question. But I know for sure there's a 'thermal break' in the even more massive floor above the basement. There are 3 more zones of PEX in that floor, and the thermal break separates the garage floor zone (which sits above the tracking room) from other 2 zones in the rest of the floor. The thermal break was necessary to insulate the cooler garage floor from the warmer living space (in the cold months), but we're also hoping it will help keep vibrations from passing through to some small extent. I don't believe they put anything like that in the basement slab. The only place that one might be needed would be the doorway, I would think the ICF provides more than enough insulation / isolation around the slab everywhere else for the basement slab. I have a picture of the slab pour in progress at the very bottom of Post [
="http://recording.org/threads/building-to-begin-spring-09-icf-shell.36560/page-4#post-296580"]#75[/
] and don't see anything in place that would act as a break in the doorway.
I hope I answered your question somewhere in there. It's late and the sun will be coming up soon.